Al Showaib Real Estate manages the Deira Tower Building. Should any repairs be required, clients can contact Mechline Eurotek Contracting, and the matter will be promptly attended to.
Â
Reference to the Frequent complaint on train chiller tripping we had carried out testing of the building Main Earth system.
Â
Removing the existing 4 nos. earth pit covers the building external area.
Remove the old corrode rods and accessories.
Â
New vertical boring and install new copper bonded rods and accessories, after installation , check the earthing Parameters log it.
Â
Put back the earth pit cover.
Â
Consequently, a service request was received from the site. Mechline Eurotek Contracting has delivered a quotation for the essential repairs at a competitive price and successfully completed the project within the agreed-upon timeframe.